Big Digital Energy Hood County AI Data Center
Overview
Big Digital Energy’s Hood County site is a current correction candidate because TYPE3’s map data predates the company’s July 2026 disclosure. TYPE3’s map data calls the project announced, records zero MW, and places it in Cleburne, Texas, while the facility name uses Hood County. Big Digital says it completed an acquisition through a 50/50 joint venture with 10NetZero. The filing describes an approximately 50-acre site with 17 MW of operational power, a phased path to as much as 111 MW of grid capacity subject to ERCOT validation, and potential total buildout of up to 300 MW using existing natural-gas infrastructure for behind-the-meter generation.
These values answer different questions. Seventeen MW is operational power in the company filing. Up to 111 MW is a potential grid pathway subject to validation. Up to 300 MW is potential total buildout. None is a promise of customer-available power, and the development disclosure does not establish a completed AI campus or contracted demand. The filing places the approximately 50-acre site less than 40 miles from Dallas-Fort Worth, while TYPE3’s map data uses a Cleburne point within the broader Hood County designation. That difference calls for broad location language rather than a more precise public address.
For Hood County, the practical status question is whether the 17 MW operational figure leads to validated grid capacity, additional buildout, or a documented customer commitment. ERCOT validation, permits, and energization remain separate milestones. Until those milestones are independently documented, the record remains conflicting even though the company now reports operational power.
Questions
How much power is operating at the Hood County site?
Big Digital’s July 2026 filing reports approximately 17 MW of operational power.
Is the site a 300 MW data center?
No operating conclusion follows from that figure; 300 MW is potential total buildout.
What is the relationship with 10NetZero?
Big Digital says the site is held through a 50/50 joint venture with 10NetZero.
Sources
Nearby facilities
Browse
Saved views, watchlists, and alerting for the live grid map are on the way. Leave your email and we'll let you know the moment member access opens.
✓ You're on the list. We'll be in touch.
This state sits outside ERCOT and outside the survey. Sponsoring one funds the work of charting it — pulling its interconnection queue, large loads, and price data onto the map.
Design mockup. No wallet, exchange account, or mailing list is connected — nothing can be sent and nothing is collected.