Project Patriot — Proposed Granbury Digital Campus
Overview
Project Patriot is a proposed digital-infrastructure campus in Granbury, Hood County, associated with Dallas-based Bilateral Energy and partners. The project website describes an approximately 2,000-acre campus, closed-loop water planning, high-capacity fiber, and self-generated islanded power intended to operate independently of the local electric grid. It also says the project is evaluating a future interconnection that could export surplus electricity. These are developer design claims, not evidence of energized data-center load.
The location and approval record require explicit qualification. The project overview lists 1225 Meadow Wood Road, while the FAQ identifies 2801 West US Highway 377 and former Knox Ranch land. Granbury’s official project page states that, as of August 6, 2026, the city had received a concept plan but not development plans; its FAQ separately says the city had not approved, permitted, or authorized data-center construction as of July 28, 2026. The developer’s FAQ also refers to a July 2025 TCEQ approval for the electrical generating facility. A power-plant permit does not establish data-center approval or operating status.
The map page should therefore use a conflict state and link to both the developer and city sources. Do not publish aggregator MW figures, infer campus IT load from the generation concept, or present the islanded-power claim as a completed grid condition. Project Patriot is valuable as a high-intent project page precisely because it separates proposed scope, regulatory status, power-generation claims, and unresolved legal or municipal questions.
Questions
What is Project Patriot?
Project Patriot is a proposed digital-infrastructure campus in Granbury, Texas, developed by Bilateral Energy and partners. Developer materials describe AI, cloud, fiber, on-site power, and a large phased campus, but the project is not verified as an operating data center.
How much power will Project Patriot use?
No verified data-center IT-load or operating MW figure is available. The developer describes self-generated islanded power and a possible future interconnection, while any power-generation permit must remain separate from data-center capacity.
Is Project Patriot operating or approved?
Operation is not verified. Granbury’s official information says the city had not approved or permitted a data center and had not received development plans as of its published 2026 dates. The developer’s project materials describe ongoing planning and community engagement.
Sources
Nearby facilities
Browse
Saved views, watchlists, and alerting for the live grid map are on the way. Leave your email and we'll let you know the moment member access opens.
✓ You're on the list. We'll be in touch.
This state sits outside ERCOT and outside the survey. Sponsoring one funds the work of charting it — pulling its interconnection queue, large loads, and price data onto the map.
Design mockup. No wallet, exchange account, or mailing list is connected — nothing can be sent and nothing is collected.