Equinix DA12 Campus — Dallas, Texas
Overview
DA12 is the parent project record for Equinix’s new Dallas campus at 1550 West Mockingbird Lane, Dallas, Texas 75235. TDLR registration TABS2026006348 identifies DA12-1 as a four-story, 372,517-square-foot data center with an estimated February 2026 start and October 2027 completion. A separate TDLR registration, TABS2026006556, identifies DA12-2 at the same address as a later interior fit-out with a September 2027–March 2028 schedule and 158,293 square feet in scope. Both filings show review complete, which is a regulatory project status, not proof of commissioning.
Equinix’s public reporting lists DA12 phase one at approximately 3,700 cabinets, a Q2 2028 delivery target, and $837 million of investment. Those figures describe planned project scope and investment; they do not establish energized capacity, critical IT load, current consumption, or customer-available space. The campus page should also avoid adding DA12-1 and DA12-2 investment or floor area into a single operating-capacity number. Each child phase needs its own schedule and verification state.
The parent page has clear search value because it answers the campus question while preventing duplicate pages. Use “planned,” “under development,” or “project” language until construction and service readiness are independently confirmed. Link to DA12-1 and DA12-2 as child records, and keep the campus distinct from nearby Equinix DA11, Infomart, and unrelated Mockingbird or Stemmons facilities. The Dallas location is verified by regulatory filings; the operating state and power profile remain unknown.
Questions
What is Equinix DA12 Campus?
It is Equinix’s planned Dallas data-center campus at 1550 West Mockingbird Lane. The campus contains separate project records for DA12-1 and DA12-2, which should be linked as child pages rather than merged into one building profile.
How much power will Equinix DA12 have?
The cited sources publish planned cabinets, floor area, schedules, and investment, but not a verified MW or critical-IT-load figure. Do not infer power from the $837 million phase-one investment or from the buildings’ square footage.
Is Equinix DA12 operating?
No operating status is verified in the cited sources. TDLR filings show the projects have completed regulatory review, while Equinix and industry sources describe future delivery. Construction, energization, commissioning, and customer availability should remain separate fields.
Sources
Nearby facilities
Browse
Saved views, watchlists, and alerting for the live grid map are on the way. Leave your email and we'll let you know the moment member access opens.
✓ You're on the list. We'll be in touch.
This state sits outside ERCOT and outside the survey. Sponsoring one funds the work of charting it — pulling its interconnection queue, large loads, and price data onto the map.
Design mockup. No wallet, exchange account, or mailing list is connected — nothing can be sent and nothing is collected.