Aligned LBB Campus — Abernathy, Texas
Overview
TYPE3’s map data identifies Aligned LBB Campus as a wholesale/build-to-suit campus at County Road 315 and Hi-Line Road near Abernathy, with Announced status and 0 MW. Aligned’s current Caprock page names LBB-01 at 1498 County Road 315 and describes dedicated power infrastructure, 2 MW UPS lineups, N+1 block redundancy, liquid-cooling capability, and closed-loop chilled water.
A TDLR filing for ADC-LBB01 lists 1421 FM 54, Abernathy, a 190,694-square-foot new construction project, $425 million estimated cost, and Review Complete status. Public project material describes a 313-acre campus, six planned buildings, 1,650,000 square feet, 540 MW planned capacity, and LBB-01 targeted for first-quarter 2027 service. These are building and campus planning layers, not current energized IT load or customer availability.
Keep Aligned LBB/Caprock separate from the unrelated Abernathy campus associated with TeraWulf/Fluidstack. Use 540 MW as planned campus scope only and reconcile 1498 County Road 315 with the TDLR 1421 FM 54 filing before publication.
Aligned’s LBB-01 page supplies useful building-level design details, but those details do not establish that the broader six-building campus is energized. The address difference may reflect parcel, phase, or filing scope; it should be resolved from Aligned or the permitting record before a location page is treated as a precise facility profile.
Questions
What is Aligned LBB Campus?
It is Aligned Data Centers’ Caprock campus near Abernathy in Hale County. LBB-01 is the first named building and is separate from another unrelated Abernathy project.
How much power will Aligned LBB have?
Public project reporting describes 540 MW of planned campus capacity. That is not current operating load, delivered utility power, or available customer IT capacity.
Is Aligned LBB operating?
No operating load was verified. LBB-01 targets service in 2027, while TYPE3’s map data remains Announced and 0 MW.
Sources
Nearby facilities
Browse
Saved views, watchlists, and alerting for the live grid map are on the way. Leave your email and we'll let you know the moment member access opens.
✓ You're on the list. We'll be in touch.
This state sits outside ERCOT and outside the survey. Sponsoring one funds the work of charting it — pulling its interconnection queue, large loads, and price data onto the map.
Design mockup. No wallet, exchange account, or mailing list is connected — nothing can be sent and nothing is collected.